PROPELLER SHAFT INSPECTION
PROPELLER SHAFT INSPECTION
SM2515150
id031500149400
1.Remove the propeller shaft. (See PROPELLER SHAFT REMOVAL/INSTALLATION [(US)].)
2.Measure the propeller shaft center runout using the dial gauge.
|
Propeller shaft maximum runout
No. |
Specification (reference) |
---|---|
1
|
0.8 mm {0.031 in}
|
2
|
1.0 mm {0.039 in}
|
-
• If it exceeds the maximum specification, replace the propeller shaft as a single component. (See PROPELLER SHAFT REMOVAL/INSTALLATION [(US)].)
3.Inspect the play and rotation of the joint by turning the universal joint in the directions shown by the arrows.
|
-
Propeller shaft rotation torque
-
0.3—1.0 N·m {3.1—10 kgf·cm, 2.7—8.8 in·lbf}
-
• If it is not within the specification, replace the propeller shaft. (See PROPELLER SHAFT REMOVAL/INSTALLATION [(US)].)